Financial statements a surety and a bank want to see

California, November 2026Last verified November 25, 2026

In one sentence: sureties and banks judge a contractor on three documents, the balance sheet, the income statement and the work-in-progress schedule, and on how much a CPA stands behind them.

The three statements and what each shows
Balance sheet, income statement, WIP schedule.

Balance sheet

What the company owns and owes on one date. Sureties look hardest at:

  • working capital: current assets minus current liabilities;
  • net worth (equity);
  • receivables that are old or doubtful;
  • debt and who it's owed to.

Income statement

Revenue, cost of work and overhead over a period. The question is whether the company makes money consistently, and whether gross profit holds up as volume grows.

The WIP schedule

The work-in-progress schedule lists every open job:

ColumnMeaning
Contract valueIncluding approved changes
Estimated total costCurrent estimate at completion
Cost to dateSpent so far
Percent completeCost to date / estimated total cost
Earned revenueContract value × percent complete
Billed to dateWhat's been invoiced
Over / under billingBilled minus earned

Overbilling (billed more than earned) means you have the owner's cash in advance; it's a liability, and too much can hide a losing job. Underbilling (earned more than billed) means you've done work you haven't billed, often unsigned change orders or a job going wrong. Sureties read both closely.

Levels of CPA work

  • Compilation: the CPA formats your numbers, no assurance.
  • Review: the CPA does limited checks and gives limited assurance.
  • Audit: full testing and an opinion.

Larger bonding programs usually require a review or audit, prepared by a CPA who knows construction and uses percentage-of-completion accounting.

PM notes

The WIP schedule is only as good as the estimated costs to complete. Update them honestly every quarter. See Job costing: knowing what each job really made.

Common mistakes

  • Giving a surety tax returns instead of construction financial statements.
  • Optimistic cost-to-complete numbers that hide a losing job.
  • A CPA without construction experience.

For learning only, not legal, tax, accounting or financial advice. Laws, amounts and deadlines change: check the official sources linked in each article, and talk to your CPA, attorney, surety agent or insurance broker before you decide.