Cores and other destructive checks

Last verified November 25, 2026

In one sentence: a core is the reference: a sample of the actual concrete, tested in a lab for strength and examined for what's inside, used to calibrate the non-destructive methods.

A core location, the core and the tests run on it
Locate, drill, label, test.

When to core

Planning

  • Locate bars first (see Cover meters and rebar locating and Ground-penetrating radar) and avoid cutting them, and never cut post-tensioning tendons.
  • Core where stresses are low and the structure can spare it; the engineer of record should agree on locations.
  • Diameter at least about 3 times the maximum aggregate size; 100 mm (4 inch) is common.
  • Enough cores for a statistical result: often at least three per area of concrete being assessed.

Testing strength

ASTM C42 covers obtaining and testing drilled cores: conditioning, trimming the ends, capping, and correcting for the length-to-diameter ratio. Core strength is usually lower than the strength of standard cylinders made from the same concrete, and codes such as ACI 318 and ACI 562 say how to judge it.

Other things a core shows

  • Depth of carbonation (phenolphthalein).
  • Chloride content at different depths.
  • Petrographic examination for alkali-silica reaction, freeze-thaw damage, air content.
  • Thickness and layering.

After coring

Fill the hole with a suitable repair mortar, label each core with location and orientation, and photograph it before it goes to the lab.

Common mistakes

  • Coring through a bar and weakening the member.
  • Too few cores to say anything about the concrete.
  • Not recording the core's location and orientation.

For learning only, not engineering advice. Inspections, test methods and their interpretation belong to qualified, certified people working to the standards and the owner's procedures that apply.