Browse Structural inspection

Visual inspection and access

Last verified November 25, 2026

In one sentence: visual inspection finds most problems, as long as it's systematic, close enough to see, and backed by measurements and photos someone else can follow.

The tools of a visual inspection and the ways to get close
Hand tools for measuring, equipment for reaching.

Being systematic

  • Follow a fixed order: span by span, element by element, the same direction each time.
  • Use a defect numbering system tied to drawings or a grid.
  • Compare every finding with the previous report: new, same, worse.

The basic kit

  • Measuring: tape, folding rule, crack width gauge or comparator card, calipers, level, plumb line.
  • Seeing: flashlight, binoculars, mirror, borescope for cavities and boxes.
  • Probing: hammer for sounding concrete and checking bolts, scraper and wire brush to clean steel, pick.
  • Recording: camera with a scale or ruler in the frame, tablet or field sheets, chalk or crayon to mark defects.

Getting close enough

MethodGood for
LaddersLow members, short spans
Lifts (boom, scissor)Undersides of short and medium bridges, building façades
Under-bridge inspection truckUndersides reached from the deck, with traffic control
Rope accessTall piers, cable stays, places a vehicle can't reach
Boats and diversPiers and foundations in water
DronesOverall views and hard-to-reach surfaces; they find areas to inspect closely, not replace hands-on work
Confined space entryBox girders, culverts, vaults, with gas monitoring and a permit

Recording what you see

For every defect: location, type, size (length, width, area, depth), condition state and a photo. A photo without a location and a scale is of little use next time.

Safety

Fall protection, traffic control, confined space procedures and working over water each need their own plan. On a bridge, the inspector's biggest risk is usually the traffic.

Common mistakes

  • Inspecting from the ground what the scope says must be inspected hands-on.
  • Photos without a scale or location.
  • Rushing the underside because the access window is short.

For learning only, not engineering advice. Inspections, test methods and their interpretation belong to qualified, certified people working to the standards and the owner's procedures that apply.