In one sentence: on a federal-aid job you follow both the federal Davis-Bacon rules and California prevailing wage law, and you pay whichever rate is higher for each craft.

State and federal rules side by side on a federal-aid job
Both apply; the higher rate wins.

How to tell

The contract says so: a federal-aid project number, federal wage decisions bound into the special provisions, and the FHWA-1273 "Required Contract Provisions" attached. FHWA-1273 must be included, word for word, in every subcontract too.

Two sets of rates

  • Federal wage decision (Davis-Bacon), published for the county and type of construction, included in the bid documents.
  • California prevailing wage determination from DIR.

For each classification, pay the higher of the two, including fringe benefits, and make sure the classification exists in both or is properly matched.

What FHWA-1273 adds

  • Nondiscrimination and equal employment opportunity requirements.
  • Davis-Bacon wage and payroll requirements, with weekly submission of certified payroll to the agency.
  • Posting of wage rates and notices on the job site.
  • Rules against convict labor, kickbacks and false statements.
  • Subcontracting limits: the prime usually must perform a minimum share of the work (often 30%) with its own forces.
  • Safety and health requirements.

Payroll

Weekly certified payroll on the federal form or an equivalent with the same information, to the agency, plus California's electronic filing with DIR. One payroll system can serve both if it captures everything.

Other federal pieces

  • Buy America: steel, iron and, increasingly, manufactured products must be produced in the United States unless a waiver applies. Material certificates matter.
  • DBE: see DBE requirements on federal-aid jobs.
  • Interviews: the agency may interview workers on site to check wages.

PM notes

Federal-aid labor compliance is reviewed during the job, not only at the end. Treat the weekly payroll as a deliverable like a submittal.

Common mistakes / what agencies actually check

  • Paying the state rate when the federal one is higher for a classification, or the reverse.
  • Subcontracts that don't physically include FHWA-1273.
  • Missing Buy America certifications for steel products.

For learning only, not legal advice. Rules change and each agency adds its own: always check the contract, the agency and the current law, and ask a construction attorney when money or a license is at stake.