Browse Public works contracting

Claims and disputes on public contracts

California law as of November 2026Last verified November 25, 2026

In one sentence: most disputes are settled as change orders; when they aren't, the contract's notice and protest steps and the Public Contract Code 9204 claim process decide whether you get paid, so follow them exactly.

From a disagreement to a claim decision
Notice first, documents always, deadlines everywhere.

Before a claim: notice and protest

Almost every public contract requires prompt written notice when you believe something is extra work or a delay, and a written protest if the engineer disagrees. Caltrans' Standard Specifications set a detailed process and deadlines for this; local agencies have their own. Missing a notice deadline can waive the claim, however good it is. See Change orders and potholing findings.

Public Contract Code 9204

For California public works, PCC 9204 sets a claim process for a contractor's claim for time, payment or a disputed amount:

  1. Submit the claim in writing by registered or certified mail, with reasonable documentation.
  2. The agency reviews it and, within 45 days, provides a written statement of the disputed and undisputed portions. The period can be extended by mutual agreement.
  3. The agency pays any undisputed portion within 60 days of its statement.
  4. If you disagree, you may demand an informal meet and confer; the agency schedules it within 30 days.
  5. What remains disputed goes to nonbinding mediation, unless both sides agree otherwise.
  6. Unpaid claim amounts accrue interest as the statute sets.

A sub without a contract with the agency can ask the prime to present its claim; the prime must answer within 45 days whether it did.

Documenting a claim

  • Daily reports describing the issue as it happened. See Daily reports and documentation.
  • Photos with dates and locations.
  • Labor, equipment and material records for the disputed work, kept separately.
  • Correspondence and RFIs.
  • A schedule analysis for delay: what was critical and why.

PM notes

Start a separate cost code the day something looks like extra work, even if you expect a quick change order.

Common mistakes / what agencies actually check

  • Waiting until the end of the job to give notice.
  • Mixing disputed and normal work in one cost code.
  • A claim without a schedule analysis when time is part of it.

For learning only, not legal advice. Rules change and each agency adds its own: always check the contract, the agency and the current law, and ask a construction attorney when money or a license is at stake.