The forms, registrations and documents a contractor runs into on California public works, what each one is for, who issues or receives it, and the article that explains it.
Bidding and award Before and right after the bid opening
| Form or document | What it is for | From | Article |
|---|---|---|---|
| Notice to bidders | The advertisement: work, bid date, license class, bond and where to get the documents | Agency | Read |
| Bid form (bid proposal) | Your prices by item or lump sum, signed | Agency | Read |
| Bid bond | Bid security, usually 10% of the bid | Surety | Read |
| Subcontractor list | Subs above one-half of 1% of the bid, with license and DIR numbers | Prime contractor | Read |
| Addendum acknowledgement | Shows you received every change to the bid documents | Prime contractor | Read |
| Non-collusion declaration | Statement that the bid was made without collusion | Prime contractor | Read |
| DBE commitment | On federal-aid jobs with a goal: which DBEs do what work, for how much | Prime contractor | Read |
| Bid protest | Written challenge to another bid or a rejection, before award | Bidder | Read |
Labor and payroll Prevailing wage, apprentices and certified payroll
| Form or document | What it is for | From | Article |
|---|---|---|---|
| DIR registration (PWCR) | Lets a contractor bid and work on public works; renewed by fiscal year | DIR | Read |
| PWC-100 | The agency's registration of the project with DIR | Awarding body | Read |
| Prevailing wage determination | The wage and fringe rates for each craft and county | DIR | Read |
| Certified payroll record | Weekly payroll by worker, filed electronically with DIR | Each employer | Read |
| Statement of compliance | Signed certification attached to each certified payroll | Each employer | Read |
| DAS 140 | Contract award information sent to apprenticeship programs | Each employer | Read |
| DAS 142 | Request for dispatch of an apprentice | Each employer | Read |
| Federal wage decision | Davis-Bacon rates bound into federal-aid contracts | U.S. Department of Labor | Read |
| FHWA-1273 | Required provisions in every federal-aid contract and subcontract | FHWA | Read |
Contract and payment Bonds, insurance, payments, changes and closeout
| Form or document | What it is for | From | Article |
|---|---|---|---|
| Performance bond | Guarantees completion of the work, usually 100% | Surety | Read |
| Payment bond | Guarantees payment to subs, suppliers and workers, usually 100% | Surety | Read |
| Certificate of insurance and endorsements | Proof of coverage and additional insured status | Insurance broker | Read |
| Progress estimate (pay application) | Monthly request for payment for work in place | Prime contractor | Read |
| Prompt payment certification | Monthly report of payments to all subs on federal-aid jobs | Prime contractor | Read |
| 20-day preliminary notice | Protects a lower-tier party's payment rights | Sub or supplier | Read |
| Stop payment notice | Requires the agency to hold funds for an unpaid claimant | Unpaid claimant | Read |
| Conditional and unconditional releases | Waivers exchanged for payments, on the statutory forms | Sub or supplier | Read |
| Claim (PCC 9204) | Written claim for time or money, sent by registered or certified mail | Prime contractor | Read |
| Notice of completion | Recorded notice that starts the payment-remedy deadlines | Awarding body | Read |
Nothing matches.
For learning only, not legal advice. Rules change and each agency adds its own: always check the contract, the agency and the current law, and ask a construction attorney when money or a license is at stake.