Browse Procore guide

Progress billing and retention

Based on Procore's public help pages, November 2026Last verified November 25, 2026

In one sentence: Procore's Invoicing tool builds your monthly bill to the owner from the prime contract's schedule of values and collects your subs' invoices against their commitments, with retention on both.

Sub invoices, owner invoice and the Caltrans progress estimate
Collect, review, bill, reconcile with the RE's estimate.

Owner invoices

  • Built from the prime contract's schedule of values: work completed this period, materials stored, retention.
  • On a unit-price Caltrans job, the SOV lines follow the bid items and quantities.
  • Approved prime contract change orders appear as lines once executed.

Subcontractor invoices

  • Subs (as invoice contacts) submit against their subcontract's schedule of values, or you create the invoice on their behalf.
  • You review, approve or return for revision.
  • Retention can be set and released per line; Procore also supports sliding-scale retention.

Lining up with Caltrans

Caltrans pays from the RE's monthly progress estimate, based on quantities the inspector measures, not from your invoice. So:

  1. Track quantities weekly with the inspector.
  2. Build your owner invoice in Procore from the same quantities, as your internal record.
  3. When the RE's estimate arrives, compare line by line and resolve differences.
  4. Pay subs their share within the time state law requires once you're paid. See Paying subcontractors and suppliers on time.

Retention on California public works is generally capped at 5%, and the prime can't hold more from subs than the agency holds from it. See Progress payments and retention.

Supporting documents

Keep certified payroll, lien releases and insurance current for each sub; many GCs require them before approving a sub invoice. Procore has compliance features for this, and Procore Pay adds payment and lien-waiver handling where it's used.

In Procore's own help

Invoicing. Procore's help pages are the reference for how each screen works today.

Common mistakes

  • Billing from your own quantities without reconciling with the RE's estimate.
  • Holding more retention from subs than Caltrans holds from you.
  • Approving sub invoices without current certified payroll.