Closeout package checklist
In one sentence: the closeout package is the proof of what you built, and the job isn't finished until it is delivered and accepted.
Checklist
| Document | Notes |
|---|---|
| As-built plans | Every change marked, with locations and depths |
| Fiber splice diagrams | Matching the field and the labels |
| Test results | Electrical, fiber and functional tests |
| Material certifications | Certificates of compliance for materials that need them |
| Battery certifications | Model, install date, warranty |
| Concrete tickets | For foundations and encasements |
| Warranty documents | With start dates |
| Equipment manuals | One set per device type, or as the contract requires |
| Configuration files | Final switch, router and device settings |
| Serial number list | By location |
| Final CPM schedule | Updated to actual dates |
| Acceptance records | Punch list closed, sign-offs |
Final quantities
Agree on the final measured quantity of every unit-price item. Daily reports and measurements support them. See Daily reports and documentation.
PM notes
Build the package from day one. File certificates with each submittal, tests as they are run, as-builts as changes happen. See Phase 12: Project closeout and delivery.
Common mistakes / what Caltrans actually checks
- As-builts drawn from memory at the end.
- Manuals thrown away with packaging.
- Warranty start dates not agreed.