Browse Caltrans electrical

Project lifecycle: the twelve phases of a Caltrans electrical job

Not yet verified against the current edition

In one sentence: a job moves from paper to pipe to wire to equipment to tests, and each phase depends on the one before it.

The twelve phases of a job grouped into paper, underground, structures, systems and acceptance
The twelve phases, with procurement and documentation running alongside.

The flow

Design review → RFIs → submittals → procurement → underground conduit → pull boxes → foundations → poles and cabinets → conductors and fiber → equipment → configuration → testing → Caltrans acceptance → punch list → closeout.

PhaseWhat happensPM focus
1. Phase 1: Preconstruction and design reviewRead the contract, find conflicts, submit, order long-lead itemsSubmittals, RFIs, baseline schedule
2. Phase 2: Underground constructionSurvey, potholing, trenching or boring, conduitUtility conflicts, lane closures
3. Phase 3: Pull boxes and foundationsPull boxes, vaults, cabinet and pole foundationsInspections before concrete
4. Phase 4: Structure installationPoles, cabinets, solar assembliesDeliveries arriving in order
5. Phase 5: Cable installationConductors, fiber and communication cableConduit proven clear first
6. Phase 6: Equipment installationSwitches, routers, cameras, power equipmentApproved equipment only
7. Phase 7: Fiber splicing and terminationFusion splicing, termination, fiber testsSplice plan and test records
8. Phase 8: Network and system configurationIP addresses, VLANs, remote accessCaltrans network requirements
9. Phase 9: System testingElectrical, communication and functional testsTest reports
10. Phase 10: Caltrans acceptance testingCaltrans witnesses testsScheduling with the RE
11. Phase 11: Punch listFix every deficiencyClosing items fast
12. Phase 12: Project closeout and deliveryAs-builts, certificates, warranties, final quantitiesGetting paid in full

How procurement runs through it

Procurement isn't a phase; it runs alongside all of them. Long-lead equipment ordered in phase 1 has to arrive in phases 4 to 6. Late equipment is the most common reason an electrical job finishes late. See Procurement and long-lead items.

Four systems, one job

Everything you order supports one of four systems: civil (conduit, concrete, pull boxes), electrical (conductors, breakers, grounding), communications (fiber, cable, switches, routers) and power (utility service, or solar and batteries).

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.