Conduit: types, sizes and fittings

Verify the edition named in your contractNot yet verified against the current edition

In one sentence: conduit is the empty pipe that protects every conductor and fiber on the job, and it is usually the largest quantity you install.

Types

Cross-section of a conduit trench showing pavement patch, aggregate base, backfill, warning tape, tracer wire, conduits and bedding
A conduit trench, from the pavement patch down to the bedding. Layers and depths follow your contract.

The specifications name the conduit allowed for each use. In general terms:

  • Rigid non-metallic (PVC), Schedule 40 or 80: the usual choice underground.
  • Rigid steel (galvanized): where more protection is needed, such as exposed runs, structures and some crossings.
  • Coated rigid steel and flexible conduit for specific locations, as the specifications and plans allow.

Which type goes where comes from Section 86, the Special Provisions: what they change and why they win and the plans. Sizes are shown on the plans or the conduit schedule.

Materials ordered with it

ItemWhat it is for
Elbows (22.5°, 45°, 90°)Change direction; sweep radius matters for fiber
CouplingsJoin conduit sections
Expansion fittingsLet conduit move with temperature, for example on bridges
Bell ends and bushingsProtect cables where conduit enters a box
Pull tape (mule tape)Left in the conduit to pull cable later. See Pull tape, tracer wire and warning tape
InnerductSubdivides a conduit for fiber
Sand bedding, slurry or concreteBedding and encasement as specified

Installation notes

Side view of a conduit run between two pull boxes with couplings, elbows under a utility, an expansion fitting and pull tape
A conduit run from box to box. Every bend adds pulling tension, so the total bend between boxes is limited.
  • Depth, slope and bedding follow Section 86 and the plans.
  • Keep runs clean: cap open ends during work.
  • Prove each run clear (mandrel or swab) before cables are pulled, and when the contract requires it, before it is buried.
  • Leave pull tape in every empty conduit.

PM notes

Conduit is often paid by the linear foot by size and type. Keep good daily records of footage installed; final quantities come from them. See Daily reports and documentation.

Common mistakes / what Caltrans actually checks

  • Using a conduit type not allowed for that location.
  • Too many bends in one run between pull boxes.
  • Open conduit ends filling with dirt during construction.
  • No pull tape left in spare conduits.