Phase 7: Fiber splicing and termination
In one sentence: phase 7 turns pulled fiber into working links, and the test records from it are what prove the links work.
What happens
- Fusion splicing fiber to fiber in splice closures in vaults or pull boxes, and at the cabinets.
- Splice trays organize the splices; every fiber goes to a known position.
- Termination at patch panels in the cabinets, with connectors on the field side and jumpers to the equipment.
- Splice records: which fiber goes where, following the splice diagram on the plans.
Testing
- OTDR traces show each splice and connector along the fiber and its loss.
- Power meter (insertion loss) tests measure the total loss end to end.
The contract sets which tests, at which wavelengths, in which directions, and the loss limits. See Fiber optic communications.
The question this phase answers: is there continuity from the field device back to the TMC?
PM focus
Fiber splicing is often a specialty subcontractor. Agree early on the test format Caltrans wants and on who produces the as-built splice diagram.
Common mistakes / what Caltrans actually checks
- Test results in a format Caltrans does not accept, requiring a retest.
- Splice diagrams that don't match the field.
- Dirty connectors causing high loss: clean and inspect every one.