Browse Caltrans electrical

Ramp metering

Verify the edition named in your contractNot yet verified against the current edition

In one sentence: a ramp meter is a small signal on an on-ramp that lets cars onto the freeway one or two at a time, timed from what the detectors see.

Plan view of an on-ramp with meter signals, demand, passage, queue and mainline detectors
The parts of a ramp meter.

Main parts

PartWhat it does
Ramp meter controller and cabinetRuns the metering rate. See Equipment cabinets
Meter signal headsRed/green signals at the stop line
DetectionDemand, passage, queue and mainline detectors. See Vehicle detection
SignsAdvance warning signs, sometimes with flashers
CommunicationLink to the TMC for monitoring and rate changes. See Network equipment: switches, routers, SFPs and cellular

How it works

Detectors on the ramp and freeway tell the controller how much traffic there is. The controller sets the rate, and the TMC can monitor and change it remotely.

PM notes

  • Detector layout and lane numbering must match the plans exactly; the TMC reads them by number.
  • Plan the turn-on with Caltrans operations staff.

Common mistakes / what Caltrans actually checks

  • Detectors wired to the wrong inputs.
  • Turning on without communication to the TMC.

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.