Procurement and long-lead items
In one sentence: procurement turns approved submittals into material on site at the right time, and long-lead items are where schedules slip.
Typical long-lead items on electrical jobs
- Controller and equipment cabinets.
- Poles, mast arms and anchor bolts.
- Changeable message signs and cameras.
- Batteries, especially lithium batteries with shipping rules.
- Network equipment: switches, routers, specific SFP modules.
- Fiber cable in specific fiber counts.
The cycle
- Quote: send suppliers the specification and plan references, not just a part number.
- Submit the quoted product. See Submittals: what Caltrans expects.
- Purchase order as soon as it is approved, or earlier with the supplier's agreement for very long lead times.
- Track fabrication and shipping dates every week.
- Receive: check the delivery against the PO and the approved submittal; note damage on the ticket.
- Store safely, and keep certificates and manuals for closeout.
Ordering bulk material
For conduit, pull boxes, conductors and fittings, ask the foremen what is left before reordering, and keep a running takeoff against what is installed. See Daily reports and documentation.
PM notes
Put procurement in the schedule with real lead times. A missing cabinet stops a system as surely as a missing crew.
Common mistakes / what Caltrans actually checks
- Asking for quotes with only a part number.
- Not tracking fabrication dates after the PO.
- Accepting a substitute that was never approved.