Material pricing and supplier quotes

Last verified November 25, 2026

In one sentence: send suppliers a clear list early, compare quotes line by line against the specs, and protect the bid against long lead times and price changes.

Requesting, leveling and using material quotes
Request, receive, level, choose, carry.

Requesting quotes

  • Send each supplier the list from your takeoff with spec references and sheet numbers, plus the special provisions sections that apply.
  • Ask for unit prices, lead times, validity date, freight and exclusions.
  • Ask early: a supplier who gets the list two days before the bid prices it in a hurry.

Leveling quotes

Put quotes side by side, item by item:

CheckWhy
Same items and quantitiesMissing items look cheap
Spec complianceApproved products, Caltrans requirements, certifications. See Submittals: what Caltrans expects
Lead timeMust fit the schedule. See Procurement and long-lead items
Validity and escalationHow long the price holds
Freight and deliveryTo the yard or the site
ExclusionsWhat the supplier didn't price

Long-lead and high-value items

Controllers, cabinets, poles, cameras, changeable message signs and some fiber equipment can take months. Check lead time against the working days and the contract's start, and note any risk.

Escalation

If quotes are valid only for a short time and the job won't order for months, add an allowance for price changes, or get the supplier to hold prices.

Sales tax

Price materials including sales tax at the rate where the work is done, unless the contract says otherwise.

Federal-aid jobs

Federal-aid contracts carry Buy America requirements for iron, steel and other products. Confirm with suppliers that their products comply. See Federal-aid jobs: Davis-Bacon and FHWA-1273.

PM notes

Keep the leveled quote sheet. When you win, it's the purchasing plan, and suppliers will expect to hear from you first.

Common mistakes / what Caltrans actually checks

  • Comparing quote totals without checking that they cover the same items.
  • Assuming a quoted product is approved under the special provisions.
  • No escalation allowance on a job that orders months after bid.

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.