In one sentence: the project plans show what to build on this job and where; the electrical sheets are the ones your crew will live in.

A simplified electrical plan sheet with legend, notes, stationing, symbols, callouts and title block
What to read on an electrical plan sheet, and in which order.

How a plan set is organized

A Caltrans plan set is a stack of sheets grouped by discipline. A typical order is: title sheet and location map, typical cross sections, layouts, construction details, stage construction and traffic handling, drainage, utilities, then the specialty sheets such as electrical, signs and striping, and structures. Each sheet has a title block with the sheet number, the total number of sheets, the contract number and the engineer's stamp.

The electrical sheets

Electrical sheets usually include:

  • Electrical legend and abbreviations: the symbols for pull boxes, conduit, poles, cabinets and devices. Read it first; symbols differ between districts and designers.
  • Plan sheets (layouts): where each pull box, conduit run, pole and cabinet goes, with stationing and offsets.
  • Schedules and details: conductor and conduit schedules, pole and equipment schedules, wiring diagrams, cabinet details and system block diagrams.
  • Communication sheets on ITS jobs: fiber routes, splice diagrams and network diagrams.

The plans refer to standard details by Standard Plan number instead of drawing them. See Standard Plans: the ES (electrical) series.

How a PM uses them

When the plans disagree

If the plans conflict with the Special Provisions: what they change and why they win, the Special Provisions govern. If the plans conflict with the field (a utility, a slope, a sign in the way), write an RFI. See Writing RFIs.

Common mistakes / what Caltrans actually checks

  • Skipping the electrical legend and misreading a symbol.
  • Scaling dimensions instead of using stationing and written dimensions.
  • Taking off quantities from one sheet and missing the schedule on another.
  • Not keeping a marked-up set during construction, then rebuilding the as-builts from memory.