Browse Caltrans electrical

Equipment, traffic control and indirect costs

Last verified November 25, 2026

In one sentence: the costs that aren't installed work (equipment, traffic control, mobilization, supervision, bonds and insurance) often decide whether a freeway electrical job makes money, so price them from the schedule, not as a percentage.

The layers of a bid
Direct work, equipment, job overhead, bonds and insurance, company overhead, profit.

Equipment

  • List the equipment each crew needs (trencher, backhoe, bore rig, bucket truck, crane, compressor, generator) and how many days.
  • Owned equipment at your internal rate; rented equipment at quote plus delivery. See Equipment: buy, rent or lease.
  • Price by days on the job, including idle days between closures.

Traffic control

On freeway electrical work, traffic control is often a major cost:

  • check whether it's a separate bid item or included in others;
  • count closures by type (shoulder, lane, ramp, full) and number of nights;
  • get a quote from a traffic control sub, or price your own crew and equipment;
  • include changeable message signs or flaggers where required.

Mobilization and field overhead

  • Mobilization: moving equipment and setting up; check the Bid Item List for a mobilization item and its limits.
  • Field overhead: superintendent, project trucks, yard or storage, temporary facilities, testing, surveying, safety, cleanup.
  • Price field overhead per working day or per month of the schedule.

Schedule and working days

The contract sets the working days. A schedule drives field overhead and equipment cost, so build at least a rough one: closures available per week, crews, sequence. Know the liquidated damages per day.

Bonds, insurance, company overhead and profit

PM notes

Indirect costs are where low bids lose money. Compare your total indirects with past jobs of similar length.

Common mistakes / what Caltrans actually checks

  • Field overhead as a percentage instead of per day of schedule.
  • Traffic control priced as if every night had a full closure window.
  • Forgetting idle equipment days between closures.