Electrical quantity takeoff
In one sentence: a good takeoff counts and measures every component on the electrical sheets by system and location, adds what the plans imply but don't show, and checks the totals against the quantity sheets.
Set up before counting
- Organize the takeoff by bid item and system, then by location (station range, interchange, ramp).
- Use the same cost codes as your job costing. See Job costing: knowing what each job really made.
- Keep a list of every plan sheet and mark it when done.
What to take off
| Component | Measure | Watch for |
|---|---|---|
| Conduit | Length by size, type and method (trench, bore, structure-mounted) | Method changes cost far more than length; riser and bend allowances. See Conduit: types, sizes and fittings and Trenching vs. directional boring |
| Pull boxes | Count by type and size | Traffic-rated boxes, extensions, grounding. See Pull boxes and vaults |
| Conductors and cables | Length by size and type, run by run | Slack at boxes and poles, vertical runs, the number of conductors per run. See Conductors and cables |
| Fiber optic cable | Length by count, splices, terminations | Slack loops, splice closures, testing. See Fiber optic communications |
| Foundations | Count by type | Depth, rebar, anchor bolts, concrete. See Foundations: cabinet, pole and sign |
| Poles and standards | Count by type | Mast arms, luminaire arms, lead time |
| Equipment | Count by type | Cabinets, controllers, detection, cameras, signs |
| Removals and modifications | Count and describe | Existing systems to keep running |
What the plans don't show
- Slack, waste and splices.
- Traffic control needed to reach each location.
- Testing and documentation. See Electrical testing.
- Temporary systems to keep existing lighting or signals working.
Checking the takeoff
- Compare your totals with the quantity sheets on the plans; explain every big difference.
- Have someone else check the largest items.
- Walk or drive the site if you can: access, existing conditions, conflicts.
PM notes
Save the takeoff with sheet references. When you win, it becomes the material order list and the foreman's quantity budget.
Common mistakes / what Caltrans actually checks
- Measuring conduit length but not the installation method.
- No allowance for conductor slack and waste.
- Trusting the quantity sheets without your own count.