Service equipment and utility power

Verify the edition named in your contractNot yet verified against the current edition

In one sentence: the service is where the utility's power becomes Caltrans's power, and getting it energized is often on the critical path.

Power flow from the utility through the meter, main disconnect and breakers to the circuits
How power gets from the utility to the circuits.

What it includes

ItemWhat it is for
Service enclosure or pedestalHouses the meter, main disconnect and breakers
Meter (when required)Measures energy for the utility bill
Main disconnect and breakersIsolate and protect circuits
Service conductorsFrom the utility point of connection to the enclosure
GroundingGround rods and bonding at the service. See Grounding and bonding

Details are on the Standard Plans: the ES (electrical) series and the project plans.

Utility coordination

The utility (for example, the local power company) decides the point of connection and schedules the connection. That usually takes an application, a service request from the agency, and inspection. Lead times can be long.

PM notes

  • Start the service request in phase 1; ask the Resident Engineer who files it on this contract.
  • Plan temporary power or a generator if equipment must run before the service is energized.
  • Sites with no practical utility service use solar. See Solar power and LiFePO4 batteries.

Common mistakes / what Caltrans actually checks

  • Starting the utility service request too late.
  • Enclosure installed in a different location than the utility approved.

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.