Reading the Bid Item List
In one sentence: the Bid Item List says what you'll be paid for and how it's measured, so before pricing, know exactly what work each electrical item includes and which work is paid somewhere else or not at all.
Unit price and lump sum
- Unit price items are paid by measured quantity (each, linear foot, cubic yard). Your price times the final measured quantity is what you get.
- Lump sum items are paid as one amount for everything described. On Caltrans projects, electrical systems are often paid as a lump sum per system, such as a lighting system, a signal and lighting system or a ramp metering system.
Caltrans' design guidance says that when electrical work is paid by lump sum, all the work shown on an electrical plan view sheet is included in a single bid item. So the lump sum carries everything on that sheet: conduit, pull boxes, conductors, foundations, poles, equipment, testing, unless the specs pay it elsewhere.
Where to look
- Bid Item List: item number, description, unit, quantity.
- Electrical plan sheets ("E", "ED" and "EQ" sheets) and quantity sheets: what's in each system. See Project plans: sheet types, legends and electrical sheets.
- Special provisions: the measurement and payment clause for each item. See Special Provisions: what they change and why they win.
- Standard Specifications: Sections 86 and 87 for electrical work. See Caltrans Standard Specifications: structure and how to read them.
Cost breakdown for lump sum items
The Standard Specifications (Section 9-1.16, Progress Payments) provide for a cost breakdown of lump sum items, which the Resident Engineer uses to pay progress. Plan your lump sum so it can be broken down sensibly later; Caltrans asks the RE to correct unbalanced unit costs in the breakdown before approving it.
Questions to ask before pricing
- Which work is paid in which item, and which is included in others?
- Is anything shown on the plans but paid in no item (so you carry it inside another)?
- Are there state-furnished materials?
- Are there supplemental work items or force account?
- What do the addenda change?
Send questions through the Caltrans bidder inquiry process before the deadline; answers apply to all bidders.
Official sources
Caltrans Construction Manual, Section 86.
Common mistakes / what Caltrans actually checks
- Pricing a lump sum system without reading what its plan sheets include.
- Missing work that's paid in no item.
- Ignoring addenda that change quantities or items.