Reading the Bid Item List

Last verified November 25, 2026

In one sentence: the Bid Item List says what you'll be paid for and how it's measured, so before pricing, know exactly what work each electrical item includes and which work is paid somewhere else or not at all.

What a bid item covers
Unit price items, lump sum systems, and work paid elsewhere.

Unit price and lump sum

  • Unit price items are paid by measured quantity (each, linear foot, cubic yard). Your price times the final measured quantity is what you get.
  • Lump sum items are paid as one amount for everything described. On Caltrans projects, electrical systems are often paid as a lump sum per system, such as a lighting system, a signal and lighting system or a ramp metering system.

Caltrans' design guidance says that when electrical work is paid by lump sum, all the work shown on an electrical plan view sheet is included in a single bid item. So the lump sum carries everything on that sheet: conduit, pull boxes, conductors, foundations, poles, equipment, testing, unless the specs pay it elsewhere.

Where to look

Cost breakdown for lump sum items

The Standard Specifications (Section 9-1.16, Progress Payments) provide for a cost breakdown of lump sum items, which the Resident Engineer uses to pay progress. Plan your lump sum so it can be broken down sensibly later; Caltrans asks the RE to correct unbalanced unit costs in the breakdown before approving it.

Questions to ask before pricing

  1. Which work is paid in which item, and which is included in others?
  2. Is anything shown on the plans but paid in no item (so you carry it inside another)?
  3. Are there state-furnished materials?
  4. Are there supplemental work items or force account?
  5. What do the addenda change?

Send questions through the Caltrans bidder inquiry process before the deadline; answers apply to all bidders.

Official sources

Caltrans Construction Manual, Section 86.

Common mistakes / what Caltrans actually checks

  • Pricing a lump sum system without reading what its plan sheets include.
  • Missing work that's paid in no item.
  • Ignoring addenda that change quantities or items.

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.