Phase 4: Structure installation
In one sentence: in phase 4 the job becomes visible: poles stand up and cabinets go on their foundations.
What happens
- Poles: signal and lighting standards, mast arms, CCTV poles and communication poles, set on cured foundations and plumbed.
- Solar assemblies: panel mounts and battery enclosures at sites without utility power. See Solar power and LiFePO4 batteries.
- Equipment cabinets: set on foundations, sealed and grounded. See Equipment cabinets.
PM focus
- Deliveries in order: poles and cabinets are long-lead items and need storage or same-day setting.
- Lifting plans and lane closures for setting poles near traffic.
- Damage on arrival: inspect finishes and record any damage before signing the delivery ticket.
- Shop drawing match: height, arm length and bolt pattern match the approved submittal.
After this phase, the structures exist, but they aren't wired.
Common mistakes / what Caltrans actually checks
- Accepting a damaged pole or cabinet without noting it on the delivery ticket.
- Setting a pole before the foundation has cured.
- A cabinet that does not match the approved submittal.