Phase 2: Underground construction

Phase 2Verify the edition named in your contractNot yet verified against the current edition

In one sentence: phase 2 builds the empty pathway every future system will use, and it is where most surprises are found.

What happens

Cross-section of a conduit trench showing pavement patch, aggregate base, backfill, warning tape, tracer wire, conduits and bedding
A conduit trench, from the pavement patch down to the bedding. Layers and depths follow your contract.

PM focus

Directional boring in three steps: pilot bore, reaming, and pulling the conduit back under a road and around a potholed utility
Directional boring: pilot bore, ream, then pull the conduit back. Pothole the utilities the bore crosses first.
  • Lane closures booked and traffic control set up as approved.
  • Water pollution control BMPs in place before digging.
  • Daily reports that record what was found, especially utility conflicts and delays. See Daily reports and documentation.
  • Conduit proven clear (mandrel or swab) before it is covered when the contract requires it.

At the end of this phase, the pathway exists but nothing is in it.

Common mistakes / what Caltrans actually checks

  • Digging before locates are complete.
  • Moving a route around a utility without an approved RFI.
  • Not recording delays from unmarked utilities in the daily report.
  • Covering conduit that was never proven clear.

For learning only. Not affiliated with or endorsed by Caltrans, and not a contract interpretation: always refer to the contract documents for your project.