Phase 8: Network and system configuration
In one sentence: in phase 8 the hardware is programmed so that each device can talk to Caltrans.
What is configured
- Switches (managed industrial Ethernet or fiber switches): ports, VLANs, management addresses.
- Cellular routers at sites without fiber: carrier, VPN or tunnel settings Caltrans specifies.
- IP addresses for every device, from the plan Caltrans provides.
- Device settings: cameras, detectors, signs and controllers set up to report to the TMC.
What is verified
- Communication paths from each device to the TMC.
- Remote access works the way Caltrans requires.
- Security settings: default passwords changed, unused ports disabled, firmware as approved.
PM focus
Get the IP plan and network requirements from Caltrans early: they are often the last piece to arrive. Many projects are physically finished but stay open until networking works. See Network equipment: switches, routers, SFPs and cellular.
Common mistakes / what Caltrans actually checks
- Waiting until the end to ask Caltrans for the IP plan.
- Leaving default passwords on network equipment.
- Not saving the final configuration files for the closeout package.